Iconic Air Force Academy chapel to remain closed for several more years

The U.S. Air Force Academy announced Thursday that its Cadet Chapel — Colorado’s most-visited man-made tourist attraction and an iconic structure at the campus north of Colorado Springs — will remain closed for massive renovations until early 2027, more than three years longer than originally expected.

The discovery of more asbestos than anticipated or budgeted for in the original $158 million project increased costs by $60 million and bumped the already-delayed completion date by three years.

“There were no notations of the asbestos in the original contract documents,” said Alex Delimont, a senior project manager with JE Dunn construction. “Unfortunately, when that initial survey was done, there were just limitations to where that survey could access.”

Delimont explained that, until workers were able to remove material from the structure — built in 1962 – they didn’t know what they were facing as far as the scope of asbestos abatement.

Duane Boyle, the campus architect at the U.S. Air Force Academy, talks Thursday about the delays in the renovation of the Cadet Chapel due to additional asbestos abatement. (Christian Murdock, The Gazette)
Duane Boyle, the campus architect at the U.S. Air Force Academy, talks Thursday about the delays in the renovation of the Cadet Chapel due to additional asbestos abatement. (Christian Murdock, The Gazette)

“And in those pockets additional material was found. And additionally in locations where it wasn’t intended to be installed originally, we found pockets of material as well,” Delimont said. “That was likely just due to the nature of not understanding the hazards of the material when it was originally installed.”

The chapel closed in September 2019, for a renovation project that was expected to shutter the iconic house of worship for at least three years. In December of last year, The Gazette reported there would be a delay due to the discovery of an increased amount of asbestos.

That challenge turned out to be bigger than expected.

“The effort is so labor-intensive, it’s just going to take a fair amount of time for them to complete the abatement and allow the rest of the project to continue,” said Carlos Cruz-Gonzalez, the USAFA’s director of logistics and engineering.

Crews work on the cranes Friday, Aug. 7, 2020, that will be used to construct a large hanger, similar to the structure at Denver International Airport, over the U.S. Air Force Academy Cadet Chapel as part of the complete restoration and renovation of the chapel designed by American Architect Walter Netsch. (Christian Murdock, The Gazette)
Crews work on the cranes Friday, Aug. 7, 2020, that will be used to construct a large hanger, similar to the structure at Denver International Airport, over the U.S. Air Force Academy Cadet Chapel as part of the complete restoration and renovation of the chapel designed by American Architect Walter Netsch. (Christian Murdock, The Gazette)

Renovations to the chapel are being done under the cover of a boxy, white “cocoon” that allows work to continue year-round. Delimont said that pandemic-related material and worker shortages haven’t been a factor in the delay.

“Fortunately, the project has been lucky in regards to material impacts from COVID,” said Delimont. “We … were fortunate in that we purchased ahead of time. The status of the project — it’s classification as essential — helped us to avoid many of those impacts.”

Cruz-Gonzalez said that the feedback he’s received so far has been perhaps disappointed, but overwhelmingly supportive.

“People understand that a project like this is going to take a fair amount of time. It’s going to be disruptive,” he said. “Of course people would have wanted the chapel to open closer to ‘23, ‘24, but they also understand that we’ve got to get it done.”

And get it done right.

Air Force Academy architect Daniela Lawrence climbs the scaffolding to the top of the 150-foot U.S. Air Force Academy Cadet Chapel Friday, Aug. 7, 2020, while touring the the chapel restoration with a group from the Denver Modernism Week. More than 50 semi-truck were used to deliver all the inside scaffolding that will allow crews to catalog and restore all the aluminum panels and stained glass. The chapel designed by American Architect Walter Netsch was named a U.S. National Historic Landmark in 2004. (The Gazette, Christian Murdock)
Air Force Academy architect Daniela Lawrence climbs the scaffolding to the top of the 150-foot U.S. Air Force Academy Cadet Chapel Friday, Aug. 7, 2020, while touring the the chapel restoration with a group from the Denver Modernism Week. More than 50 semi-truck were used to deliver all the inside scaffolding that will allow crews to catalog and restore all the aluminum panels and stained glass. The chapel designed by American Architect Walter Netsch was named a U.S. National Historic Landmark in 2004. (The Gazette, Christian Murdock)
A group from the Denver Modernism Week conference stand outside the U.S. Air Force Academy Cadet Chapel Friday, Aug. 7, 2020, as they tour the $158-million restoration and renovation project of the 1962 chapel to learn about Saving Modernism History. Campus Architect Duane Boyle gave the tour. (The Gazette, Christian Murdock)
A group from the Denver Modernism Week conference stand outside the U.S. Air Force Academy Cadet Chapel Friday, Aug. 7, 2020, as they tour the $158-million restoration and renovation project of the 1962 chapel to learn about Saving Modernism History. Campus Architect Duane Boyle gave the tour. (The Gazette, Christian Murdock)
–>

Iconic Air Force Academy chapel to remain closed for several more years

The U.S. Air Force Academy announced Thursday that its Cadet Chapel — Colorado’s most-visited man-made tourist attraction and an iconic structure at the campus north of Colorado Springs — will remain closed for massive renovations until early 2027, more than three years longer than originally expected.

The discovery of more asbestos than anticipated or budgeted for in the original $158 million project increased costs by $60 million and bumped the already-delayed completion date by three years.

“There were no notations of the asbestos in the original contract documents,” said Alex Delimont, a senior project manager with JE Dunn construction. “Unfortunately, when that initial survey was done, there were just limitations to where that survey could access.”

Delimont explained that, until workers were able to remove material from the structure — built in 1962 – they didn’t know what they were facing as far as the scope of asbestos abatement.

Duane Boyle, the campus architect at the U.S. Air Force Academy, talks Thursday, April 21 about the delays in the renovation of the Cadet Chapel due to additional asbestos abatement. (Christian Murdock, The Gazette)
Duane Boyle, the campus architect at the U.S. Air Force Academy, talks Thursday, April 21 about the delays in the renovation of the Cadet Chapel due to additional asbestos abatement. (Christian Murdock, The Gazette)

“And in those pockets additional material was found. And additionally in locations where it wasn’t intended to be installed originally, we found pockets of material as well,” Delimont said. “That was likely just due to the nature of not understanding the hazards of the material when it was originally installed.”

The chapel closed in September 2019, for a renovation project that was expected to shutter the iconic house of worship for at least three years. In December of last year, The Gazette reported there would be a delay due to the discovery of an increased amount of asbestos.

That challenge turned out to be bigger than expected.

“The effort is so labor-intensive, it’s just going to take a fair amount of time for them to complete the abatement and allow the rest of the project to continue,” said Carlos Cruz-Gonzalez, the USAFA’s director of logistics and engineering.

On Aug. 7, 2020, crews work on the cranes used to construct a large hangar, similar to the structure at Denver International Airport, over the U.S. Air Force Academy Cadet Chapel as part of the complete restoration and renovation of the chapel designed by American Architect Walter Netsch. (Christian Murdock, The Gazette)
On Aug. 7, 2020, crews work on the cranes used to construct a large hangar, similar to the structure at Denver International Airport, over the U.S. Air Force Academy Cadet Chapel as part of the complete restoration and renovation of the chapel designed by American Architect Walter Netsch. (Christian Murdock, The Gazette)

Renovations to the chapel are being done under the cover of a boxy, white “cocoon” that allows work to continue year-round. Delimont said that pandemic-related material and worker shortages haven’t been a factor in the delay.

“Fortunately, the project has been lucky in regards to material impacts from COVID,” said Delimont. “We … were fortunate in that we purchased ahead of time. The status of the project — it’s classification as essential — helped us to avoid many of those impacts.”

Cruz-Gonzalez said that the feedback he’s received so far has been perhaps disappointed, but overwhelmingly supportive.

“People understand that a project like this is going to take a fair amount of time. It’s going to be disruptive,” he said. “Of course people would have wanted the chapel to open closer to ‘23, ‘24, but they also understand that we’ve got to get it done.”

And get it done right.

Air Force Academy architect Daniela Lawrence climbs the scaffolding to the top of the 150-foot U.S. Air Force Academy Cadet Chapel Friday, Aug. 7, 2020, while touring the the chapel restoration with a group from the Denver Modernism Week. More than 50 semi-truck were used to deliver all the inside scaffolding that will allow crews to catalog and restore all the aluminum panels and stained glass. The chapel designed by American Architect Walter Netsch was named a U.S. National Historic Landmark in 2004. (Christian Murdock, The Gazette)
Air Force Academy architect Daniela Lawrence climbs the scaffolding to the top of the 150-foot U.S. Air Force Academy Cadet Chapel Friday, Aug. 7, 2020, while touring the the chapel restoration with a group from the Denver Modernism Week. More than 50 semi-truck were used to deliver all the inside scaffolding that will allow crews to catalog and restore all the aluminum panels and stained glass. The chapel designed by American Architect Walter Netsch was named a U.S. National Historic Landmark in 2004. (Christian Murdock, The Gazette)
A group from the Denver Modernism Week conference stand outside the U.S. Air Force Academy Cadet Chapel Friday, Aug. 7, 2020, as they tour the $158-million restoration and renovation project of the 1962 chapel to learn about Saving Modernism History. Campus Architect Duane Boyle gave the tour. (Christian Murdock, The Gazette)
A group from the Denver Modernism Week conference stand outside the U.S. Air Force Academy Cadet Chapel Friday, Aug. 7, 2020, as they tour the $158-million restoration and renovation project of the 1962 chapel to learn about Saving Modernism History. Campus Architect Duane Boyle gave the tour. (Christian Murdock, The Gazette)
Organ pipes at the Air Force Academy Cadet Chapel frame the pews and the altar. (Parker Seibold, The Gazette)
Organ pipes at the Air Force Academy Cadet Chapel frame the pews and the altar. (Parker Seibold, The Gazette)

Iconic Air Force Academy chapel to remain closed for several more years

Officials met with media Tuesday to discuss he delays in the renovation of the U.S. Air Force Academy Cadet Chapel due to additional asbestos abatement efforts. The completion date has been moved to 2026, instead of 2023 as originally planned when the renovations began in 2019. (Video: Stephanie Earls/The Gazette)


PREV

PREVIOUS

Polis signs bill banning Colorado colleges, universities from withholding diplomas over student debt

Colleges and universities in Colorado are no longer allowed to withhold diplomas or transcripts because of a student’s unpaid debt – thanks to legislation Gov. Jared Polis signed into law on Thursday. House Bill 1049 prohibits higher education institutions from refusing to provide transcripts or diplomas to students who have unpaid fees, parking tickets or other […]

NEXT

NEXT UP

Newest Denver library to be named after well-known local artist

The Denver Public Library Commission announced Thursday that its newest branch will be named after Bob Ragland, a teacher and award-winning artist who died April 10, 2021. Ragland was known to stroll to the library every day and would sketch a drawing along the way. “Bob Ragland was an artist, library supporter and a community leader and […]


Welcome Back.

Streak: 9 days i

Stories you've missed since your last login:

Stories you've saved for later:

Recommended stories based on your interests:

Edit my interests